Project management priorities and challenges, a critical perspective on the PMBOK's methodology

 

 

 

 


Amine RAMIL


 

 

Table of Contents

I.    Project justification    3

II.    Management philosophy    5

III.    Organizational framework     6

IV.    Project Management Priorities:  9

V.    Project management challenges:  10

VI.    Tailoring     17

References   19

 

 


 

 

Abstract:

The purpose of this research is to critically analyse the use of PMBoK methodology’s process groups on the light of its main rival, PrInCE2. Starting with questioning project justification philosophy in both methodologies, this paper goes through their views of projects’ organization and challenges to conclude on the best practices for tailoring and combining methodologies to fit projects’ contexts.

 

According to a recent research study (Singh and Lano, 2014), 61% of IT projects in 2012 did not deliver the expected features and functions within budget and schedule. The average magnitude of budget over-run was 30%, and 1 in 6 projects went more than 50% over budget. In fact, managing projects’ constraints is not the purpose of organizations. Generating sustainable business benefits is. Many projects delivered on time and within budget often fail to deliver the expected profitability or growth outcomes. In order to make those dramatic statistics take a turn for the better, research and experimentations are conducted on the subject of project management methodologies.

Charvat (2003) defines methodology as a "set of guidelines or principles that can be tailored and applied to [a] specific situation”. Scholars and practitioners group project management methodologies into two main families (Chin and Spowage, 2010):

-       Project management guides to knowledge, standards and procedures (known as PMMs: Project Management Methodologies) are dynamic and flexible guides to the best practices and tools that are adaptive to different environments.

Best practices have been created by international organizations, such as Project Management Institute (PMI) or APM, as a result of efforts "to codify the area of knowledge required for competent project management” (Meredith and Mantel, 2012).

-       Project management sequenced methodologies (known as ADMs: Application Development Methodologies) are project management guides that provide design and development guidance [together with a proposed lifecycle structure] (Chin and Spowage, 2010)

The champion of PMMs is the Project Management Institute’s Guide to Project Management Body of Knowledge (PMI, 2013). The British Office of Government Commerce’s Projects in Controlled Environments version 2 (PrInCE2) is the industry standard for the second category. APMBOK (PMI, 2013), PROS and other methodologies are used in a lesser extent (Chin and Spowage, 2012).

 

Here is a high-level comparison between the two main standards:

 

(Chin and Spowage, 2010)

As we can notice in this summary, PrInCE2 is highly prescriptive and all its processes should be applied while PMBoK (PMI, 2013) gives higher flexibility to project managers.

Both approaches aim at a better management of projects’ lifecycles, products, constraints and variables. However, the purpose of project management, organizational frameworks, philosophies and tools vary from one approach to another. This difference impacts the way project managers initiate, execute, and deliver projects. The purpose of this research is to critically analyse the PMBoK’s (PMI, 2013) view of projects’ justification, organization and management compared to its main rival PrInCE2 and other methodologies if needed. The main project management related challenges, especially the role of the “Business Case” as a project justification for both methodologies, and the subsequent financial management will be discussed. Light will also be shed on the importance of tailoring PMMs and ADMs to specific organizational environments (Karaman and Kurt, 2015).

      I.         Project justification

The purpose of projects is to create new services or products that generate value for the different stakeholders within some agreed constraints and conditions. However, 65% of organizations do not check if their initiatives are aligned with their business objectives. 7 out of 8 companies use outdated and inaccurate information when taking Go / No Go decisions for their projects (Singh and Lano, 2014). So how do PMBoK (PMI, 2013) and PrInCE2 (OGC, 2012) tackle project justification? and are there any possible synergies between the two approaches?

According to the PMBoK (PMI, 2013), project management is part of a wider picture. Projects should belong to portfolios. A portfolio is a group of projects, programs, sub-portfolios, and operations managed as a group to achieve strategic objectives. Consequently, the business justification of a project comes mainly from its contribution to the realization of the portfolio’s objective. That is why, in the PMBoK (PMI, 2013) authors’ view, the role of project management is limited to the delivery of the project’s product within its constraints. Success is measured according to the delivery on time within budget [Delivery on time and within budget are the success measurement criteria]. Hence, the project manager's role is limited to managing the project resources in order to achieve that objective. Nevertheless, the project manager has full decision-making power, together with the sponsor, on the way those resources are used to achieve the project’s objectives (Karaman and Kurt, 2015).

A business case is still required during the initiation processes. Its objective is to show how the project is going to generate the expected financial outcomes. Mainly based on a cost-benefit analysis, the business case in the PMBoK’s methodology can be an iterative process that tracks the achievement of the expected business benefits. Likewise, the Earned Value Management (EVM), which is the main tool of project financial flow up according to the PMBoK (PMI, 2013) does not take project business outcomes into consideration (Roberts and Roberts, 2017).

Project Managers using PMBoK’s (PMI, 2013) guidance without a wider portfolio management approach run the risk of delivering products or services that are not aligned with the organizational strategy. This may lead to unmet expectations in terms of business benefits and value generation (Karaman and Kurt, 2015). In real life, many projects which are considered successful fail to deliver return on investment in the long run (Munns and Bjeirmi, 1996). That is why the OGC’s PrInCE2 authors adopted a different philosophy.

“Continued business justification is one of the most important principles of PRINCE2 and it is also covered as a Theme named "Continuous Business Justification" with strong emphasis. On the contrary, it is also mentioned by PMBOK (PMI, 2013) that business case is reviewed periodically, but not as strongly as (in) PRINCE2” (KARAMAN AND KURT, 2015)

PrInCE2’s approach is centred on the business benefits of the project rather than its constraints. This importance of the business justification may be observed in three aspects of the methodology (Roberts and Roberts, 2017). To begin with, what the PMBoK (PMI, 2013) calls constrains is called variables by PrInCE2. In PrInCE2’s methodology, the constraint “resources” is replaced by the variable “benefits”. Consequently, project management success is continuously measured according to the realization of business benefits. Any project could be cancelled if the realization of the expected business benefits is not possible even if the project is delivered within its time and cost constraints. Second, the business case is used in the PMBoK’s methodology (PMI, 2013) during the initiation process group only while PrInCE2 considers it as one of its seven themes that grow with the project from its inception to the business benefits delivery after the Go Live of the project. Third, PrInCE2 replaces the PMBoK’s (PMI, 2013) constraints-centric Earned Value Management’s (EVM) KPIs by the business-benefits-centred Management of Value (MoV). MoV’s KPIs track the progress of value and business benefit creation within and beyond the boundaries of project delivery (Karaman and Kurt, 2015). Management of Value uses techniques such as “value trees”, “value profile”, value index” and other ratios to recommend the best use of time, money and resources to generate business benefits. (TSO, 2012)

In a word, PMBoK (PMI, 2013) is most concerned with the success of the project management whereas PrInCE2 is focused on the success of the project itself.

“(…) make a distinction between project success and the success of project management, bearing in mind that good project management can contribute towards project success but is unlikely to be able to prevent failure.” e.g. the Thames Barrier, the Fulmar, North Sea oil projector, Concorde” (Munns and Bjeirmi, 1996)

All things considered, PMBoK (PMI, 2013) and PrInCE2 methodologies are complementary. When it comes to project justification and business benefits measurements, PMBoK’s users can be inspired by PrInCE2’s MoV principles in order to widen their view of project performance and build a more accurate set of KPI's. Even the project management vision and philosophy can benefit from the British standard in order to link project performance to the achievement of its business benefits (Roberts and Roberts, 2017).

    II.         Management philosophy

Equally important are the role, priorities and decision-making power of the project manager. These vary from one approach to another and have an impact on the project managers’ influence and set of activities.

The PMBoK (PMI, 2013) considers the project manager as the decision-maker when it comes to resource management risk assessment and project constraints management. In contrast, PrInCE2 sees the manager more as an executer than a decision-maker. The important decisions are made by the project board (Singh and Lano, 2014).

“The project manager is responsible for day to day management of the project, within the directions set by the Executive/Project Board” (Hedeman and Seegers, 2009)

In PrInCE2’s approach, the project manager spends his time executing the board’s decisions and making MoV reporting. He/she is in charge of managing the team but his/her influence is lowered by the fact that he/she never has the final word in the important decisions (Singh and Lano, 2014). This approach, coupled with the “Management by Exception” (TSO, 2012) principle that places strict limitations on the project manager’s authority and prerogatives, may lead to people management difficulties. Comparatively, the PMBoK’s approach to human resources management allows the project manager to have more impact on his/her team which may give him/her higher chances of success (Chin and Spowage, 2010).

All in all, the PMBoK has an effective approach to the project manager's role and set of activities. However, its project justification, success criteria and management philosophy need to be completed by PrInCE2’s “business justification” and “focus on products” principles.

  III.         Organizational framework

The difference between PMMs and ADMs can also be seen clearly in their respective organizational schemes.

On the one hand, PMBoK (PMI, 2013) is a rich knowledge guide with a huge organizational framework that is structured in many different overlapping ways. This may be confusing for beginners in project management. PMBoK’s organizational approach can be divided into two categories:

1.     Chronological organization (dedicated for project lifecycle management and scheduling);

2.     Knowledge categorization

Regarding the chronological organization, the PMBoK (PMI, 2013) suggests, briefly, a lifecycle management approach and techniques that split projects into sequential phases. The phases are related to milestones or deliverables. However, the lifecycle management is described in a succinct manner in PMBoK’s section 2 and cannot be considered as a central element in this methodology. The knowledge guide is mainly structured around knowledge.

Knowledge in a PMBoK (PMI, 2013) is organized in two ways:

 

A.    Knowledge areas:

Knowledge areas classification is mainly a constraint-driven approach where knowledge is organized around the main skills that are required to manage project constraints efficiently: Time, Cost, Scope, Human Resource, Stakeholders, Integration, Risks, Procurement, Communication and Quality. This classification overlaps with another one: the process groups.

 

B.     Process groups;

In this second approach, knowledge, tools and techniques are classified according to the intended actions of the project manager. The process groups are: Initiation, Planning, Execution, Monitoring and Controlling and Closing. At first glance, this may look like a lifecycle or a chronological order. It is not. Process groups may be used iteratively and simultaneously during the different phases of a project. For instance, the “monitoring and controlling” process group and its related processes could (and should) be triggered in all project phases. In sum, the PMBoK (PMI, 2013) does not intend to propose a pre-defined project scheme or schedule. It only gives guidance that should be tailored according to the adopted management approach and projects’ sectors, organizations and conditions (Singh and Lano, 2014). Methodology tailoring aspects are discussed later in this research.

On the other hand, “PrInCE2 is a structured project management method” (reference, Hedeman and Seegers, 2009). It requires projects to be done in stages. At least, two stages are required: “Initiation” and “Delivery”. Go and No Go decisions are taken at the end of each stage. Correspondingly, PrInCE2 suggests seven processes to be followed in each stage: start-up, initiating (planning), directing, controlling stage, managing product, managing stage boundary, and closing. (Hedeman and Seegers, 2009). These 7 processes may be considered as the project’s (or stage’s) lifecycle. This is a key difference between PrInCE2 and PMBoK (Karaman and Kurt, 2015).

“The PRINCE2 process model comprises (…) distinctive management processes, namely Starting up a Project (SU), Directing a Project (DP), Initiating a Project (IP), Planning (PL), Managing Stage Boundaries (SB), Controlling a Stage (CS), Managing Product Delivery (MP), Closing a Project (CP) , which cover the full life cycle of a project.” (Singh and Lano, 2014)


 

Even if the organizational approaches of the two methodologies are different in many ways, a number of similarities can be observed. The following tables summarize the differences and similarities between the two approaches in terms of processes and process groups.

 

 Source: (Karaman and Kurt, 2015)

Karaman and Kurt (2015) argue that PrInCE2 is more comprehensive in terms of initiation, direction and delivery management activities. The British methodology has a better Quality and Configuration Management approach that is completed by ITIL service strategy recommendations.

PMBoK (PMI, 2013), however, offers more extensive knowledge and tools regarding Procurement, Scope, Time and Cost management. Similarly, Stakeholders management, Human Resource management and Communication management are covered by the PMBoK (PMI, 2013) in a far better way. More importantly, the biggest PMBoK’s  (PMI, 2013) asset is its Integration management approach. It is comprehensive and represents the core of its management philosophy.

  IV.         Project Management Priorities:

In a study covering many large organizations, Chin and Spowage (2012) discovered that the most used project management process groups are respectively: Planning, Closing and Initiation. This shows that the Project Management profession is mainly regarded as a planning role.

 Source: (Chin and Spowage, 2012)

 

A deeper dive in Stowage’s statistics shows that Risk planning, Communication planning and the Work Breakdown Structure (WBS) are respectively the most used tools and processes by project managers. Interestingly, risk management comes before breaking down the work of the project and even before planning project’s communication.

Organizations are concerned about the high amount of uncertainty that is related to new initiatives and to the projectized environments. This amount of uncertainty is exacerbated by the lack of a “Business Benefits” focus. This lack could be fixed thanks to PrInCE2’s MoV techniques and tools.

Source: (Chin and Spowage, 2012)

A failed communication means a failed project. That is why most organizations lay a high emphasis on this aspect. “Communication Planning” is the second most frequently used process. According to the PMBoK’s logic, the project manager should spend most of his time communicating and managing communication (PMI, 2013).

The third most frequently used technique is the WBS. This  is one of the most important elements of the project management cycle as it is the foundation for time management, resource allocation and consequently the project's scheduling and delivery.

In conclusion, Project Managers are more focused on key planning and risk management aspects. This is probably done at the expense of business benefits realization. A more balanced approach is suggested. The next section discusses the main challenges related to the different process groups, project phases as well as projects’ inputs and outputs, and transition to operations.

    V.         Project management challenges:

When working on this research, most of the documentation and research papers found were about “in-project” challenges. The aim of this section is to have a holistic view of the main project management challenges starting from the inception and pre-project conditions to the final closedown of the project’s product at the end of a project’s product lifecycle.

Source: (Munns and Bjeirmi, 1996)

1.     Pre-project and starting up

In the pre-project stage, the project manager can be involved in pre-sales efforts, project justification and may interact with sales people. Those aspects drive many challenges.

-        Project justification: projects are aimed at realizing new business benefits for the organization. However, outdated data, confusing features and benefits or changing environments may lead to failure to deliver such benefits. Agile Methodologies and PrInCe2 suggest a business-benefits-centred approach (Roberts and Roberts, 2017).

-        Overlapping approval mechanisms: This is very common in public and large organizations. The official sign off to start a project may be confusing and may involve stakeholders with conflicting points of view. It is recommended for organizations to adopt a unified “Project charter” approval process. The project charter represents the legal “birth certificate” of the project and allows the project manager to work with confidence and clear prerogatives (PMI, 2013).

-        Unclear goals: Unclear Goals mean that the goal is unrealistic in scope or may not be defined. Project manager may use Goal Analysis techniques to fix this issue.

 

 

Source (Sankar and Jubi, 2015)

 

-        Unclear SOW: The Statement of Work is the document that represents the legal engagement the company took vis-à-vis its customer. It is usually made by salespeople with many unprecise aspects. The role of the project management is to clarify all the points, and include (or exclude) all the hidden aspects of the project in the scope (Doraiswamy and Shiv, 2012).

Source: (Doraiswamy and Shiv, 2012)

-        Failure in stakeholder identification: Missing a stakeholder is missing requirements, perception and expectation management, and thus missing acceptance, adoption and satisfaction. The PMBoK suggests the adoption of a comprehensive stakeholder register based on stakeholder analysis and expert judgement.

Source: (Ffwdpm, 2017)

 


 

2.     Estimating and planning

As discussed previously, planning is considered as the main task of a project manager. A successful planning will contribute tremendously to the success of project management. Successful planning faces two main challenges: Scope definition, Time and cost estimation.

-        Scope definition challenges: Unclear, ambiguous or missed requirements can lead to a poorly defined scope. Failure in scope definition is fatal to projects and project management. Benefits, cost, time and resource management damage may be unrepairable. The project manager should spend enough time planning scope management, collecting requirements and defining the scope (Doraiswamy and Shiv, 2012). Agile methodologies recommend the use of prototypes for real-world scale requirement collection and understanding. Workshops, decomposition techniques and product/alternatives analysis are used to improve scope definition and work breakdown. Design thinking techniques are also combined with Agile methodology to create new iterative ways to understand stakeholders’ requirements and expectations.

-        Inaccurate time and cost estimation: One of the most critical areas of expertise of a project manager is his ability to accurately estimate the duration and the cost of each task in his project. However, no matter how expert he is, the project manager still needs to use proven techniques. The PMBoK recommends the use of estimating techniques (parametric/analogous/three-point…) coupled with estimating tools (project management software/top-down/bottom-up…) and scheduling techniques (critical chain or critical path…). Resource optimisation (levelling or smoothing) is recommended for both time and cost optimization (PMI, 2013).

-        Unmanaged risks: Risk management is a cornerstone for successful project management. Unmanaged risks may lead to total failure. Qualitative risk assessment is recommended for all projects. Categorization, urgency and impact assessment and diagramming techniques are recommended to identify, assess and plan responses for projects risks. Communicating risk is also important for managing expectations and securing management commitment. One of the great approaches to risk management is to share risk with subcontractors. This proved to be a successful strategy during the construction of terminal five at Heathrow airport (Gladden, 2012).

3.     Production (or Execution):

This is where the ideal idea of a project becomes reality. Challenges in this stage are mainly related to human aspects.

-        Failure in acquiring, retaining or managing people: The challenge with people management goes beyond skills shortage, staffing on time and assigning the right tasks to the right people. People groups have specific dynamics that scholars and professionals have been analysing for a long time. The following figure recapitulates the main models in terms of teams’ lifecycle management. Tuckman’s model is the most famous one. Peck’s model is a good complementary approach. A project manager should avoid introducing team changes during the chaos/storming stages. Management theories such as XY theory and motivation-hygiene can be used to motivate, retain and develop teams (Cameron, 2016).

Source: (Cameron, 2016).

 

 

-        Conflicts: Thomas and Kilmann (2007) recommend the use of collaborative models to resolve conflicts. Win-win approaches allow all parties to be satisfied and to avoid compromising.

-        Salespeople interference: Salespeople are valuable allies when it comes to conflict management (engaging customers’ stakeholders). However, their interference in the project management and in making commitments on behalf of the project team may lead to projects failure. This issue is generally addressed through a precise and effective communication planning. Communication channels, roles and responsibilities should be defined clearly. The customer should be informed of the scope and of the change control process (Doraiswamy and Shiv, 2012).

 

4.     Monitor and control:

While monitoring and controlling project’s work, the project manager should pay attention to scope and quality.

-        Scope control issues: One of the biggest project risks is the scope creep. The PMBoK suggest perform regular variance analysis in order to avoid it (PMI, 2013).

-        Quality issues: Delivering a product that is conform to the initial engagement is critical. The PMBoK recommends a comprehensive quality management approach that starts before the project (cos-benefit analysis), goes with it (audit, process analysis) and controls its performance with proven methods (sampling, inspection…); (PMI, 2013).

Source: PMBoK (PMI, 2013)

 

5.     Deliver/close:

The delivery and closure is the moment of truth. Unaccepted delivery means budget and cost overruns and, very probably, a total failure.

-        Rejected product: The most important challenge at the final stage is the user’s acceptance. Stakeholders satisfaction should be monitored and corrective action taken during the whole project (PMI, 2013)

-        Failed transition to operations: A successful project is able to smoothly go from project mode to operations. Two approaches are listed: Big-bang and Phased. Depending on the nature of the project, the Project Manager should choose the right approach and implement it carefully (TSO, 2007).

Source: (TSO, 2007)

 

-        Lack of support and/or maintenance: The aim of a project is to produce value during a certain (generally long) product lifecycle. Failure to deliver proper support and maintenance may lead to unsuccessful projects. ITIL service strategy (reference) is a recognized approach in the IT industry. It may inspire project managers from other sectors as well (TSO, 2012).

Source: (TSO, 2012)

In essence, the project manager should develop multidisciplinary skills to deal with the different challenges he may face in his job. A good PMM supplies him with effective tools and techniques to deal with those challenges. He needs to tailor the standard PMMs to fit his project’s context (Chin and Spowage, 2010).

  VI.         Tailoring

As reported by Chin and Spowage (2010), tailoring a project management methodology reduces the rate of project failure from 34% to 18%. Adopting a world-class project management methodology is good, but tailoring drives, statistically, more success to organizations. Therefore, what is project management methodology tailoring? How does it work and how could organizations successfully adapt its standards and create methodologies that fit their specific needs?

Charvat (2003) indicates that an efficient methodology is the one that leverages enough knowledge, tools, standards and best practices while allowing for adjustments to be performed to fit the dynamic nature of projects. PMBoK (PMI, 2013) and PrInCE2 are good examples of efficient project management methodologies.

The PMBoK (PMI, 2013) leaves it up to the project manager and his team to adapt the tools, processes and standards to the project’s organizational and sectorial contexts:

“For any given project, the project manager, in collaboration with the project team, is always responsible for determining which processes are appropriate, and the appropriate degree of rigor for each process. Project managers and their teams should carefully address each process and its inputs and outputs (PMI, 2013).”

Regarding PrInCE2, tailoring is a core concept in this methodology. This aspect is as important for the OGC’s methodology as its 7 principles, 7 themes and 7 processes. Hedeman and Seegers (2009) argue that the methodology should be adapted to fit sector-specific models and organizational culture, standards and maturity level. Project managers should also take project related parameters such as scale, complexity and risks into consideration.

PMMs can be tailored in many different ways. First, sector-driven adaptations are common. For instance, construction companies are more likely to adopt waterfall approaches while software development companies will opt for iterative lifecycles. Second, culture is also an important factor. Risk averse companies for example tend to choose more rigid mechanisms and processes (Whitaker, 2014). Third, project complexity may dictate different levels of rigor. Dell Services, a business unit of Dell Inc., uses a ranking system to categorize its projects depending on their complexity. The more complex a project is, the more rigorous the PMM applied is (APQC, 2013).

Correspondingly, Chin and Spowage (2010) propose a categorization of PMM tailoring into five levels of customization. Level One (L1) methodologies are the generic “one-fits-all” guidelines, best practices and standards such as APMBOK, PMBoK and PrINCE2. Level Two (L2) is dedicated to sector specific methodologies such as Agile, Scrum, RAD. Organization specific methodologies such as SAP ASAP, Microsoft’s MSF, IBM’s RUP are classified under Level Three (L3). The fourth level of customization (L4) encompasses project specific methodologies and Level Five (L5) is for the fully individualized methodologies.

Source: (Chin and Spowage, 2010)

In the light of this categorization, governments, sectorial institutions, organizations and individuals are advised to tailor existing methodologies to fit their specific needs in order to benefit from the full range of the existing standards’ possibilities while avoiding any useless complexity. Customized models offer better return on investment, quicker time to value and better analysing capabilities as light is shed exclusively on the necessary processes.


 

References

APQC (2013). Effective project management offices. Houston, TX: American Productivity & Quality Center. 

Cameron, E. (2016). Making sense of change management. Kogan Page Stylus.

Charvat, J. (2003). Project Management Methodologies: selecting, implementing and supporting methodologies and processes for projects. Hoboken, New Jersey: John Wiley and Sons.

Chin, C. M. M., and Spowage, A. C. (2010). Defining and Classifying Project Management Methodologies. PM World Today, 12(5), 1-9.

Chin, C. M. M., Spowage, A. C. (2012). Project Management Methodologies: A Comparative Analysis. Journal for the Advancement of Performance Information and Value, 4 (1), 106-118.

Doraiswamy, P. and Shiv, P. (2012). 50 Top It Project Management Challenges. It Governance Pub.

FFWDPM (2017). Master File - Fast Forward Project Management - FFWDPM. [online] Ffwdpm.com. Available at: http://www.ffwdpm.com/master-file.php [Accessed 28 Jun. 2017].

Gladden, R. (2012). The Project Risk Maturity Model: Measuring and Improving Risk Management Capability. Project Management Journal, 43(5), pp.101-101.

Hedeman, B. and Seegers, R. (2009). PRINCE2 2009 Edition. Zaltbommel: Van Haren Pub.

Karaman, E. and Kurt, M. (2015). Comparison of project management methodologies: prince 2 versus PMBOK for it projects. Int. Journal of Applied Sciences and Engineering Research, Vol. 4(4, 2015).

Meredith, J. and Mantel, S. (2012). Project Management: A Managerial Approach, Ninth Edition International Stud. John Wiley & Sons.


Munns, A. and Bjeirmi, B. (1996). The role of project management in achieving project success. International Journal of Project Management, 14(2), pp.81-87.

OGC (2012). Managing Successful Projects with PRINCE2. UK: The Stationary Office - Office of Government Commerce.

Patil, G. (2016). Project Management Challenges. Journal of Multidisciplinary Engineering Science and Technology (JMEST), Vol. 3(11, November - 2016).

PMI (2013). A guide to the project management body of knowledge. Pennsylvania: Project Management Institute.

Roberts, D. and Roberts, S. (2017). Management of Value and Earned Value Management – why both?. [online] Available at: http://www.apmg-international.com [Accessed 28 Jun. 2017].

Sankar, U. and Jubi, R. (2015). Project Management Challenges in Software Development. Research Journal of Management Sciences, Vol. 4(7)(18-23, July (2015).

Singh, R., and Lano, K. (2014). Literature Survey of previous research work in Models and Methodologies in Project Management. International Journal of Advanced Computer Science and Applications, 5 (9), 107-122.

Thomas, K. and Kilmann, R. (2007). Thomas-Kilmann conflict mode instrument. [Place of publication not identified]: [Xicom/CPP].

TSO, (2007). Service transition (ST). 1st ed. London: TSO (The Stationery Office).

TSO, C. (2012). ITIL Service Strategy. 3rd ed. London, GBR: The Stationery Office Ltd.

VandenBrink, R. (2010). The Life and Challenges of a Consulting Project Manager. [online] Sans.org SANS Information Security Training | Cyber Certifications | Research. Available at: https://www.sans.org/ [Accessed 28 Jun. 2017].

Whitaker, S. (2014). The Benefits of Tailoring: Making a Project Management Methodology Fit. Project Management Institute White Papers.